2001 WORK PLAN FOR THE MUWEKMA OHLONE POCKET PARK

WITH BUDGET SUMMARY ATTACHED

LAST UPDATED ON 02/25/2001

DATES

REF #

TASK

CONTACTS

Oct-Nov

10.06

Grant Award Notification

SF URP

10.15

Meeting at SLUG-work plan/budget analysis

David & Berkeley

10.20

Begin search for Subs

David

10.25

Nov-Dec

11.12

Project startup

 

 

11.1

Forward contact sheet and update website

 

 

11.1

Locate & interview candidates for fiscal agents

Building Resources. Audubon ,Renaissance Parents

 

12.1

Contact Port of SF re: permits

Carol Bach, Phil Williamson

 

12.15

Contact & interview landscape architects

Jeff Brown, Keller Mitchell ( Linda Roberson & Jackie)

 

12.30

Begin Work Plan Design

David

 

12.31

Build Islais Creek Web Site

David

 

 

 

 

Jan-Feb

 

Forward contact sheet and update website

 

 

01.02

Meet Berkeley and Sarah to discuss work plan (at SLUG)

 

 

01.01

Update and forward contact sheet and website

 

 

01.05

Start writing work plan

David

 

01.11

Contact Phil Williamson at Port of San Francisco

David

01.16

Telephone Jackie Keller & present project

David & Jackie

 

01.17

Measure and grid site for Keller Mitchell

Miscellaneous

 

01.18

Fax drawings to Keller Mitchell

David

 

01.18

Attend URP awards dinner, 6 PM, Opera House

David & neighbors

 

01.20

Site visit by Jackie Keller

 
 

01.29

Fax site drawings & plans to Port of San Francisco

Phil Williamson

 

01.24

Meeting with Tempe Priestly, for fiscal status

 
 

01.24

Contacted Jim Salerno & Joyce Stern for lis of scientests

 
 

01.25

Convert site drawings to CAD and forward to Keller

 
 

01.25

Fiscal agent paper signed by Renaissance Parents for Success & delivered to URP

Tempe Priestly, Berkeley Neblett and Daivd

 

01.26

Schedule presentaion to SF Port

Braj Norris, Dan Bell, Phil Wiliamson & David

 

01.27

Schedule presentation for SWAC

Braj Norris

 

01.28

Final budget estimates for all services

 
 

01.29

Golden Gate Audubon board meeting, fiscal agent decision

Arthur Feinstein

 

01.30

Submit final draft of work plan & budget to URP

Berkeley Neblett

 

02.01

Begin search for science specialists and appointments

 
 

02.03

E mail SF Bay Trail rough draft community ideas

Niko Latunich

 

02.05

Order site temporary signs

 
 

02.10

Heron's Head Park Stewardship meeting

David

 

02.17

Sophie Maxwell benefit @ Cocomo

David, RMC, J Rodriquez, community

 

02.22

Presentation to Port Staff

 
 

02.21

African American Awards @ the Presidio

 
 

02.16

Conduct first community meeting for project review

All parties concerned

 

02.18

Begins project revisions as needed

All parties concerned

 

02.20

Submit SF Bay Trail Planning & Construction Ideas

Niko Latunich

 

02.26

SWAC Presentation

 
 

02.27

SF Park & Rec site visit

 
 

02.28

Work Plan & Budget Meeting

 
 

02.28

Conference call with Ohlone office

 

Mar-Apr

 

Forward contact sheet and update website

 
 

03.01

Native Arts in the parks site visit

 
 

03.02

Second community meeting to present revised project

 
 

03.03

Update and forward contact sheet and website

 
 

03.03

Schedule Native American Arts in the Parks History Month Event for Islais Creek (SFNPC)

lhunter@sfneighborhoodparks.org

 

03.05

Site visit for study of installation of the Healing Pole

Francisco Da Costa & Shane Eagleton

 

03.05

Site visit by the Muwekma Ohlone Tribe

Rosemary Cambra & Monica Arellano

 

03.21

Spring Equinox Celebration!

 
       
 

04.01

Begin design for 2002 URP Grant Application-site implementation

 
 

04.01

Finish applications for other grant sources

 

May-June

 

Forward contact sheet and update website

 
       
 

06.21

Summer Solstice Celebration!

 
       
       

July- August

 

Forward contact sheet and update website

 
       
       
       

Sept-Oct

 

Forward contact sheet and update website

 
 

09.21

Autumn Equinox Celebration!

 
       
       

Nov-Dec

 

Forward contact sheet and update website

 
 

12.21

Winter Solstice Celebration!